How to Get ADU Permit in West Palm Beach: Complete 2026 Guide
Tips
December 19, 2025
minute read

How to Get ADU Permit in West Palm Beach: Complete 2026 Guide
Key Takeaways
West Palm Beach ADU permits require both zoning verification and building permits through the City Development Services office at 401 Clematis Street
Total permit timeline ranges from 4-8 weeks (best case) to 2-3 months average, with complex projects extending to 4-6 months
Permit and utility connection costs total $6,875-$40,870 depending on project scope
Palm Beach County ADU size limits are 800 sq ft for lots under 1 acre and 1,000 sq ft for larger properties, with maximum heights of 25 feet
All ADUs must meet Florida Building Code hurricane requirements—properties in High Velocity Hurricane Zones (HVHZ) face stricter wind resistance standards
Mesocore's factory-built Model E ADU includes Intertek-certified MEP systems that eliminate rough-in inspections, reducing on-site installation to just 10 days
West Palm Beach homeowners are increasingly turning to accessory dwelling units as a solution for rental income, multigenerational housing, and property value enhancement. For property owners ready to add an ADU, understanding the local permit requirements—from zoning verification through Certificate of Occupancy—is essential for a smooth project timeline.
Understanding West Palm Beach ADU Requirements
Before submitting any permit applications, you must verify that your property meets West Palm Beach's zoning and dimensional requirements. The Development Services office on the 2nd floor at 401 Clematis Street handles all zoning inquiries at (561) 822-1435.
What are the local zoning regulations for ADUs in West Palm Beach?
ADUs are typically permitted in single-family (SF) residential districts throughout West Palm Beach. However, your specific zoning designation determines what you can build. Key regulations include:
Owner occupancy requirements may apply depending on your district
Architectural compatibility with the main residence is mandatory
One ADU maximum per residential lot
Separate meters may be required or optional based on jurisdiction
Contact the Planning Division for a same-day verbal determination on your property's eligibility, or request a written zoning determination within 3-5 business days.
Are there specific size or height restrictions for ADUs?
Palm Beach County establishes clear dimensional limits for ADUs:
Maximum size: 800 sq ft for lots under 1 acre; 1,000 sq ft for lots 1 acre or larger
Maximum height: 25 feet, and cannot exceed the main dwelling's height
Minimum separation: 10 feet from the main house
Setbacks: Typically 15-25 feet for rear and side yards (verify with your specific zoning district)
Elevation: 2.5 feet above adjacent road outside flood zones; higher requirements apply in FEMA flood zones
These size limits make Mesocore's 410 sq ft Model E ADU well-suited for most West Palm Beach properties, fitting comfortably within zoning restrictions while maximizing usable living space.
What are the parking mandates for ADUs in West Palm Beach?
Parking requirements vary by district, but most ADU projects require 1-2 additional off-street parking spaces. Verify your specific parking obligations during the zoning verification phase.
Navigating the West Palm Beach ADU Permit Application Process
The permit process involves nine sequential steps, each with specific requirements, fees, and timelines. Complete documentation at each phase prevents costly delays.
Step 1: Pre-Application Zoning Verification
Where: City of West Palm Beach Development Services, 2nd Floor, 401 Clematis Street
Contact: (561) 822-1435
What to bring:
Property address and parcel ID
Preliminary site plan or sketch
Lot dimensions
Timeline: Same-day verbal guidance; written determinations in 3-5 business days
Cost: No fee for initial inquiry
Step 2: Design and Professional Plan Preparation
Florida requires sealed architectural plans from licensed professionals. Your design package must include:
Signed and sealed architectural plans
Structural drawings (per Florida Statutes Chapter 471/481)
Site plan showing property boundaries, existing structures, ADU location, setback dimensions, and parking
Electrical, plumbing, and mechanical plans
Energy code compliance calculations
Wind/hurricane resistance documentation per Florida Building Code
Timeline: 2-6 weeks for plan completion
Cost: $3,000-$10,000+ for professional design services
Step 3: Record Notice of Commencement (NOC)
Where: Palm Beach County Recording Department, County Courthouse, 205 North Dixie Highway, 4th Floor
Contact: (561) 355-2991
The NOC must be recorded before the building permit is issued. After recording, email a PDF copy to ds@wpb.org with your permit number in the subject line.
Timeline: Same-day recording
Cost: $10-$20 recording fee
Step 4: Contractor Registration
If using a contractor, submit the following documents to ds@wpb.org:
State license or County competency license
Valid local business tax receipt
Certificate of insurance (general liability)
Workers' compensation certificate or exemption
Company contact information
Timeline: 1-2 business days
Cost: No fee for registration
Step 5: Building Permit Application Submission
Submit your complete application through the Civic Access portal or in person at the Building Division on the 1st floor at 401 Clematis Street.
Required documents:
Building permit application
Signed and sealed plans (PDF for digital submission)
Property survey (less than 1 year old)
Site plan with proposed improvements
Recorded Notice of Commencement
Owner/Builder Affidavit (if owner is pulling permit)
Impact fee payment documentation
Contact: (561) 805-6700 or ds@wpb.org
Step 6: Plan Review and Revisions
Multiple city departments review your plans for code compliance:
Building envelope and structural review
Zoning verification
Electrical, plumbing, and mechanical review
Life safety and accessibility review
Energy code compliance
How to check status: Log into the Civic Access portal, navigate to your permit record, and click the "Reviews" tab.
Timeline: 2-4 weeks for initial review; 1-2 weeks per revision cycle
Step 7: Permit Issuance
Once all reviews are approved and fees paid:
Download your permit from the Civic Access portal, or
Pick up at the Building Division, 401 Clematis Street, 1st Floor
What you receive:
Permit card (must be posted at job site)
Approved plans (signed/stamped)
Required inspection list
Permit number for scheduling inspections
Timeline: 1-2 business days after final approval
Step 8: Construction and Required Inspections
Standard ADU inspections include:
Foundation/footing
Underground plumbing and electrical
Framing and rough-in (electrical, plumbing, mechanical)
Insulation and sheathing
Roofing
Final building, electrical, plumbing, and mechanical inspections
Schedule inspections: Through the Civic Access portal (available 24/7)
Inspector contacts:
Building Chief: Richard Brunelle, (561) 805-6670
Mechanical Chief: Chris Montello, (561) 805-6732
Electrical Chief: Phil Petty, (561) 805-6742
Plumbing Chief: Ryan Brown, (561) 805-6692
Step 9: Certificate of Occupancy (CO)
How to request: Email ds@wpb.org with subject line "CO Request," including your master permit number, address, and contact information.
Prerequisites:
All required inspections passed
All corrections completed
All fees paid
No open violations
Timeline: 1-2 business days after request
You cannot legally occupy or rent your ADU—or connect utilities—without a Certificate of Occupancy.
Key Building Permit Considerations for West Palm Beach ADUs
West Palm Beach falls within Palm Beach County's jurisdiction for building code compliance, which includes stringent requirements for hurricane resistance and energy efficiency.
Ensuring your ADU plans comply with Florida Building Code
All ADUs must meet the Florida Building Code (8th Edition, 2023), based on the International Building Code (IBC) and International Residential Code (IRC). Key compliance areas include:
Structural integrity per ASCE 7-22 wind load calculations
Electrical schematics meeting National Electrical Code
Plumbing diagrams per Florida Plumbing Code
HVAC specifications meeting efficiency standards
IECC energy conservation requirements
Understanding structural requirements for ADUs in hurricane zones
Palm Beach County includes High Velocity Hurricane Zone (HVHZ) designations in Miami-Dade and Broward counties, with portions of Palm Beach County requiring enhanced wind resistance. Standard requirements include:
Impact-rated windows and doors for wind-borne debris protection
Continuous roof-to-wall connections with approved hurricane straps
Enhanced roof fastening schedules for 130+ mph wind zones
Concrete footings with specific reinforcement requirements
For properties in hurricane-prone areas, documentation of wind resistance is mandatory during plan review.
The role of Intertek certification in streamlined inspections
Factory-built modular ADUs with Intertek certification can significantly reduce on-site inspection requirements. When MEP systems are pre-inspected at the factory by a certified third-party inspector, some jurisdictions eliminate the need for rough-in inspections on-site. This accelerates construction timelines and reduces the potential for failed inspections.
Financing Your West Palm Beach ADU: Permit Costs and Construction Loans
Understanding total project costs—including permits, impact fees, and utility connections—helps you plan financing effectively.
Estimating ADU permit and construction costs in West Palm Beach
Building Permit Fee:
Low Range: $75
Average: $1,500
High Range: $3,000
Plan Review Fee:
Low Range: $50
Average: $975
High Range: $1,950
Trade Permits (electrical/plumbing/mechanical):
Low Range: $225
Average: $450
High Range: $900
Impact Fees:
Low Range: $1,000
Average: $2,000
High Range: $3,000
Water/Sewer Connection:
Low Range: $1,000
Average: $3,000
High Range: $6,000
Electric Connection:
Low Range: $1,000
Average: $2,000
High Range: $3,800
Total Government Fees:
Low Range: $3,375
Average: $18,540
High Range: $28,870
Professional services (architect, engineer, survey) add $3,500-$12,000 to total project costs.
Financing options for your ADU project
Ocean Capital Lending, Mesocore's financing partner, offers financing covering land acquisition and construction costs, with conversion to traditional mortgage upon completion.
Leveraging tax incentives for ADU construction
Federal and state incentives reduce your effective ADU cost:
30% federal solar tax credit through 2032 for integrated solar systems
0% Florida sales tax on solar equipment
Property tax exemption for renewable energy installations (solar/battery don't increase taxable value)
Florida "Granny Flat" reduction of up to 20% of assessed value for senior relative (62+) occupancy
Learn more about available tax incentives for ADU construction.
Expediting Your West Palm Beach ADU Project with Modular Construction
The permitting phase—not construction—represents the primary timeline bottleneck. Once permits are approved, modular construction offers dramatic time savings.
How modular ADUs reduce construction timelines in West Palm Beach
Traditional site-built ADU construction takes 4-6 months after permitting. Modular construction compresses this to days:
Site Preparation:
Traditional Build: 1-2 weeks
Modular Build: 1-2 weeks
Foundation:
Traditional Build: 1-2 weeks
Modular Build: Included
Framing:
Traditional Build: 2-4 weeks
Modular Build: Factory-built
MEP Rough-ins:
Traditional Build: 2-3 weeks
Modular Build: Factory-installed
Finishes:
Traditional Build: 3-4 weeks
Modular Build: Factory-completed
Total On-Site Construction:
Traditional Build: 2-4 months
Modular Build: 10 days
Benefits of factory-built homes for permit compliance
Factory construction provides advantages for permit compliance:
Weather independence: 60-95% of work completed indoors eliminates weather delays
Quality control: Factory inspections at every production stage ensure code compliance
Pre-certified systems: Intertek certification of MEP systems streamlines plan review
Consistent documentation: Factory-standardized engineering simplifies structural calculations
Sustainability and Resilience for Your West Palm Beach Backyard Cottage
South Florida's climate demands both hurricane resilience and energy efficiency. Building for both protects your investment and reduces operating costs.
Designing a hurricane-resistant ADU for West Palm Beach
Florida Building Code requires ADUs to meet wind resistance standards based on location. Standard requirements include:
Impact-rated windows and doors meeting Florida Product Approval standards
Roof systems designed for 130+ mph wind loads
Continuous load path from roof to foundation
Enhanced fastening schedules for all structural connections
Mesocore's hurricane-resistant construction carries a 180 mph wind rating—exceeding HVHZ requirements and Category 5 hurricane thresholds of 157 mph.
The benefits of integrated solar power and battery storage
While Florida doesn't mandate solar for ADUs, integrated systems provide significant benefits:
Annual utility savings of $1,500-$1,820
Off-grid capability with battery storage for hurricane resilience
30% federal tax credit reducing effective system cost
Premium rental rates for energy-efficient units
Palm Beach County has approved Mesocore ADUs to operate independently from the main house—no utility hookup or separate meter required—potentially eliminating connection fees and ongoing utility expenses.
Maximizing ROI with an ADU in the West Palm Beach Market
West Palm Beach's strong rental market and housing demand create excellent conditions for ADU investment.
Generating passive income with a West Palm Beach ADU
Florida ADU rental income averages $2,200/month in metropolitan markets. A Mesocore Model E ADU priced at $129,000 can deliver:
18.4% annual ROI based on rental income
5.4-year payback period for full investment recovery
$28,500 annual rental income after 4% maintenance costs
How an ADU can increase your property value
Beyond rental income, ADUs add permanent property value through:
Additional living space documentation
Permitted, code-compliant construction
Sustainable features that appeal to environmentally-conscious buyers
Flexibility for multigenerational living arrangements
Why West Palm Beach Homeowners Choose Mesocore for ADU Projects
Mesocore's West Palm Beach factory location provides distinct advantages for local ADU projects. Factory-direct delivery within the optimal 250-400 mile range minimizes transportation costs while enabling rapid deployment.
Permit process advantages:
Intertek-certified MEP systems eliminate rough-in inspections in qualifying jurisdictions
Pre-engineered 180 mph wind resistance exceeds local building code requirements
Complete documentation package simplifies plan review
Factory quality control reduces revision cycles
Construction timeline benefits:
10-day on-site installation versus 4-6 months for traditional construction
All mechanical, electrical, and plumbing systems factory-installed and tested
Simultaneous site preparation and factory production eliminate sequential delays
Financial benefits:
Model E ADU starting at $129,000 including integrated solar and battery storage
Ocean Capital Lending partnership provides financing for land acquisition and construction
30% federal solar tax credit applies to integrated systems
Off-grid capability may eliminate utility connection fees
For West Palm Beach homeowners ready to add an ADU, Mesocore offers free consultations and factory tours at the West Palm Beach facility. Contact (561) 386-7252 or info@mesocore.com to discuss your project.
Frequently Asked Questions
What is the average cost to get an ADU permit in West Palm Beach?
Total permit and utility connection costs range from $6,875 to $40,870 depending on project scope. Government permit fees alone typically run $3,000-$6,000, with utility connections adding $3,000-$10,000+.
How long does it typically take to get an ADU permit approved in West Palm Beach?
The permitting phase takes 4-8 weeks best case, 2-3 months on average, or 4-6 months for complex projects. Initial plan review requires 2-4 weeks, with each revision cycle adding 1-2 weeks. Construction timelines vary from 10 days for modular installation to 4-6 months for traditional site-built ADUs.
Can I build an ADU on any property in West Palm Beach?
ADUs are typically permitted in single-family residential zoning districts, but specific eligibility depends on your property's zoning designation, lot size, and setback requirements. Contact the Development Services office at (561) 822-1435 to verify your property's eligibility before beginning the design process.
What are the benefits of choosing a modular ADU for my West Palm Beach property?
Modular ADUs offer faster installation (10 days versus 4-6 months), factory quality control, pre-certified MEP systems that may eliminate rough-in inspections, and weather-independent construction. Mesocore's integrated solar and battery systems can provide off-grid capability, potentially eliminating utility connection costs.
Are there any specific grants or incentives for ADUs in West Palm Beach?
Florida offers 0% sales tax on solar equipment, property tax exemptions for renewable energy installations, and the "Granny Flat" property tax reduction of up to 20% for senior relative occupancy. Federal incentives include the 30% solar tax credit through 2032. Contact Mesocore for county-specific incentive calculators.
What are the post-permit steps for starting ADU construction in West Palm Beach?
After permit issuance, post the permit card on-site and schedule required inspections through the Civic Access portal. For traditional construction, complete foundation, framing, MEP rough-ins, and finishes with inspections at each phase. For modular ADUs with factory-certified systems, the installation process is condensed to approximately 10 days with fewer required inspections. All projects require a final Certificate of Occupancy before the ADU can be legally occupied or rented.